Thu
Thu
Thu
Thu

George

Thursday°C
Thu
Thu
Thu
Thu

Wilderness

Thursday°C
Thu
Thu
Thu
Thu

Uniondale

Thursday°C
Thu
Thu
Thu
Thu

Haarlem

Thursday°C

Important numbers

Electricity044 874 3917
Water / Sanitation044 801 9262/9266
Fire 044 801 6311
Refuse Removal044 802 2900
Traffic / Licence044 878 2400 / 044 801 9315
Law Enforcement044 801 6350
GO GEORGE Call Centre0800 044 044
George Municipality Switchboard044 801 9111
Hide -
Published: 12 Aug 2019Title: CONTROLLED FIRES PLANNED DENNEOORD AND GARDEN ROUTE DAM NEXT TWO WEEKS Status: George Municipality Fire Department will be conducting controlled burns above Denneoord and around the Garden Route Dam as part of fuel reduction and veld fire management activities in August. Burns are weather and wind direction dependent, and therefor no specific dates are available.
Published: 07 Aug 2019Title: WATER UPDATE: 7 AUGUST 2019Status: Garden Route Dam Level: 72.31% Please note the dam level is currently being managed to facilitate construction to raise the spillway of the Garden Route Dam. Once completed, the heightened dam wall will increase its storage capacity by 25%. Construction is expected to be completed next year.
2
Home 2Contact usShow

Weather

George
Thursday°C
Thu
Thu
Thu
Thu

Weather

Wilderness
Thursday°C
Thu
Thu
Thu
Thu

Weather

Uniondale
Thursday°C
Thu
Thu
Thu
Thu

Weather

Haarlem
Thursday°C
Thu
Thu
Thu
Thu

Important numbers

Electricity 044 874 3917
Water / Sanitation 044 801 9262/9266
Fire 044 801 6311
Refuse Removal 044 802 2900
Traffic / Licence 044 878 2400 / 044 801 9315
Law Enforcement 044 801 6350
GO GEORGE Call Centre 0800 044 044
George Municipality Switchboard 044 801 9111
14 May 2018

Thembalethu UISP housing phase 1 finished

The first phase of the UISP housing project in Thembalethu is finished with families receiving the last houses in this phase.
Phase 1 of the UISP commenced on 27 February 2017 and was completed on 30 April 2018. The size of the houses is 42m2. A total of 150 houses have been built and handed over.
Phase 2 of the UISP commenced on 19 January 2018 with the completion date being 31 December 2018. A total of 251 houses will be built in this phase. Construction of top structures is underway and no houses have been handed over to date.
The Protea Park Housing project was approved for 71 top structures. Construction on the 71 houses commenced on 10 May 2016 and all houses were handed over to beneficiaries by 23 March 2018. The EPHP housing delivery programme was used to deliver houses in this project with the house size being 42m2. Moreki Distributors was the contractor in Protea Park.
Lawula and Marnol JV (Joint Venture) are the contractors in Thembalethu. It forms part of the Thembalethu: Upgrading of Informal Settlements Programme (UISP). The contractor also part of the phase 2. The cost of a serviced property (with all municipal services) amounts to R43 000 and the top structures R111 000.
The Enhanced People’s Housing Process (EPHP) Housing Programme was implemented in these projects, which added a lot more value to the project because the participants were also given the opportunity to have a say in the product that was delivered to them. The normal norms and standards of the Department of Human Settlements are far exceeded in this project as a 42m2 house was built and the whole house was fully tiled, with a tiled roof, aluminium windows, kitchen cabinets, outdoor lights and more.

Photo: Some of the beneficiaries of phase 1 of the UISP housing project in Thembalethu are from left, Mbewana Ntombehlubi, Vuyokazi Maketha, Nokuphumla Makeswa, Sibongile Fukuse with the keys of his house handed to him by Yandiswa Malgas (Human Settlements official: George Municipality), Nokwanda Mbelu, Gladys Magquba (Ward Committee Member of Ward 21), Siyabulelo Qashani and Nobathini Raneke.

Last published 14 May 2018